Local News Toledo

 

2014 Toledo Area Road Construction Projects

  • SR12 Bridge Replacement (Now - 7/2014): Through July, SR 12, between SR 635 and SR 590 will be closed for bridge replacement. Detour: SR 635; US 6; SR 590.
  • US23 Resurfacing (Now - 8/2014): Through August, intermittent lane restrictions are possible on US 23 between SR 105 and US 6 for resurfacing. Traffic will be maintained by flaggers.
  • SR582 Resurfacing (Now - 8/2014): Through August, intermittent lane restrictions are possible on SR 582, between SR 25 and SR 65, for resurfacing.  Traffic will be maintained by flaggers.
  • I-475 Resurfacing (Now - 10/2014): Through October, overnight from 7pm until 6am, lane restrictions are possible on I-475 from SR 25 to US 20A for resurfacing. Ramp restrictions and closures on the I-475/US 24 ramps will be announced. Weekend interstate lane restrictions will be announced. 
  • SR65 Bridge Painting (Now - 10/2014): Through September, intermittent lane restrictions are possible on the Craig Bridge (SR 65), between Front Street and Summit Street for bridge painting. 
  • SR105 Resurfacing (Now - 10/2014): Through October, intermittent lane restrictions are possible on SR 105, between US 20 and Woodpointe Drive for resurfacing. Intermittent lane restrictions are also possible on SR 105 between US 20 and Oak Street for resurfacing. Traffic will be maintained by flaggers.
  • I-280 Resurfacing and Bridge Repair (Now - 11/2014): Through November, both directions of I-280, between Ayers Road and Woodville Road, are reduced to one lane with an 11 foot lane width restriction for bridge work. Through August, the following ramps will be closed:
    • The ramp from southbound I-280 to Walbridge Road.  Detour: southbound I-280; eastbound SR 795; northbound I-280.
    • The ramp from Walbridge Road to southbound I-280. Detour: northbound I-280; northbound SR51; southbound I-280.
  • SR65 Resurfacing and Bridge Work (Now - 11/2014): Through November, lane restrictions are possible on SR 65, from W. Boundary Street (SR 25) to SR 64 (Waterville bridge) for resurfacing.  Traffic will be maintained by flaggers. Through June, SR 65, between Roachton Road and Brittney Road, will be closed for culvert replacement.  Detour: SR 64; SR 582; SR 25. Local access will be maintained.  Additional closures of SR 65 for bridge repair in this area will be announced.
  • Anthony Wayne Bridge Reconstruction (Now - 12/2015): The Anthony Wayne Bridge (SR 2) over the Maumee River in Downtown Toledo is closed through September 2015 for bridge reconstruction.  Work includes re-decking the bridge, replacing existing truss spans, substructure improvements, new street lighting and rebuilding sidewalks, railings and fencing.
  • I-475 Bridge Widening (Now - 11/2015): Replace and widen three bridges on I-475.  Bridges are located on I-475 over Wolf Creek, Norfolk Southern Railroad tracks and Angola Rd.
  • I-75 Pavement Reconstruction (Now - 7/2016): Reconstruct over 3 miles of pavement from Dorr Street to Central Ave. in downtown Toledo.
  • I-75 Widening (Now - 11/2016): Widen both directions of I-75 to three lanes from Findlay to Perrysburg. Total of four projects measuring a distance of 31.6 miles
  • McCord Rd. Railroad Grade Separation (Now - 11/2016): Build an underpass at the Norfolk Southern railroad, construct a roundabout at the intersection of McCord Rd. and North Mall Drive/Hill St.
  • I-475 Pavement Repair (6/15/2014 - 6/20/2014): Effective Sunday, June 15, through Friday morning, June 20, overnight from 8pm until 6am, intermittent short-term lane restrictions are possible on I-475, between US 24 and Secor Road, for pavement repair. 
  • SR65 Culvert Replacement (6/16/2014 - 6/27/2014): Effective, Monday, June 16, through Wednesday, June 18, SR 65, between Cross Creek Road and Tontogany Road, will be closed for culvert replacement.  Detour:  SR 235; Kellogg Road; SR 64. Local access will be maintained. Effective Thursday, June 19, through Friday, June 27, weekdays only, SR 65, between SR 582 and SR 64, will be closed for culvert replacement.  Detour:  SR 64; SR 582.  Local access will be maintained.
  • SR101 Sewer Work (6/16/2014 - 7/2014):Effective Monday, June 16, through July, SR 101, between East Perry Street and Heilman Street will be closed for sewer work. Detour: SR 18; CR 13. For more information please contact the City of Tiffin (419) 448-5401.
  • SR19 Resurfacing (6/16/2014 - 8/2014):Effective Monday, June, 16, through August, intermittent lane restrictions are possible on SR 19 between US 20 and SR 105. Traffic will be maintained by flaggers. On Monday, June 23 through Thursday, June 26, SR 19, between US 20 and SR 105, will be closed for bridge work. Detour: US 20; SR 590; SR 105.
  • SR295 Railroad Repair (6/17/2014 - 6/20/2014): Effective Tuesday, June 17, through Friday, June 20, SR 295, between Cardinal Lane and Soul Road, near the Ohio Turnpike will be closed for railroad repair. Detour: SR 2; SR 64; US 20.
  • I-75 Barrier Wall Repair (6/18/2014 - 6/19/2014):Effective Wednesday, June 18, through Thursday, June 19, daily from 8am until 3pm, lane restrictions are possible on southbound I-75, between Miami Street and Wales Road, for barrier wall repair.
  • SR109 Bridge Replacement (6/23/2014 - 8/2014): Effective Monday, June 23, through August, SR 109, between US 24 and Young Street in Liberty Center, will be closed for bridge replacement. Detour: US 24; SR 108; US 20A.
  • SR66 Bridge Repair (7/2014 - 8/2014):Through July, SR 66, between SR 2 and SR 34, will be closed for bridge repair. Detour: SR 34; SR 2.
  • I-475/US23 Safety Improvements (7/2014 - 11/2015): Safety project to improve movements at the I-475/U.S. 23 systems interchange, including adding through lanes from southbound U.S. 23 to I-475 and correcting weave movement from eastbound I-475 to southbound U.S. 23 and Central Ave.